Children’s Medical Center
- Date: 2004
- Place: Dallas, Texas
About this Project
A week previous the hospital itself underwent emergency surgery… to replace 200 feet of collapsed 6″ sewer lines. The access point for this operation was the central courtyard, right where the media would be located a week later to cover the high-profile operation of the twins!
A unique challenge with this job was that access to the courtyard was narrow and inaccessible to traditional heavy equipment. unless it were to be lifted in by helicopter. Pipe Genie systems are lightweight, collapsible and therefore portable and were able to be hand-carried into the courtyard worksite.
This was a short-time, critical job that required crews to be working round-the-clock. The courtyard surfacing had to be removed and a 20 foot deep pit needed to be hand-dug and shored in highly compacted soil. Because the sewer line was completely collapsed, rods had to be punched through in order to run chain for the pull.
Restrictive access to the worksite.
pulling unit lowered into place.
to close the wound!